Mumbai Railway Projects: Kalyan-Badlapur 52% Complete
Two key railway projects progress steadily, improving capacity and segregation of services.

Mumbai's railway network is set to receive a significant boost with two key capacity projects progressing steadily. The Kalyan-Badlapur third and fourth lines have reached 52% completion, while the Borivali-Virar fifth and sixth lines have achieved 30% progress by July-end.
The projects, being executed by the Mumbai Rail Vikas Corporation (MRVC) under MUTP 3-A, aim to create additional capacity on two of Mumbai's busiest suburban corridors and improve the segregation of local and long-distance services. The Kalyan-Badlapur project, estimated at Rs 1,510 crore, involves adding two lines alongside the existing double-line section and is targeted for completion by 2028.
Work on 31 bridges has been completed, while construction of other bridges is underway. The LC-1A and MIDC road overbridges have been completed and opened to traffic, and the MIDC pipeline bridge was completed in March 2026. At Chikhloi station, most civil work on the station and service buildings has been completed, with painting remaining.
The additional lines are expected to improve local train frequency during peak hours and provide greater flexibility for long-distance services on the Kalyan-Karjat corridor. On the Western Railway side, the Rs 2,184-crore Borivali-Virar fifth and sixth line project covers a 26-km stretch and is targeted for completion by 2029.
Land acquisition and statutory clearances have progressed, with 11.929 hectares of mangrove land at Umelman in Vasai handed over and remaining acquisition underway. Railway structures at Dahisar, Mira Road, Bhayandar, Naigaon, Nalasopara, and Vasai Road have been shifted or are nearing completion.
The MRVC officials said the additional lines will create separate capacity for suburban and long-distance trains, allowing better service planning and reducing operational conflicts on the heavily used corridor. The completion of these projects is expected to significantly improve the commuting experience for millions of Mumbaikars.
The projects are part of the larger effort to upgrade Mumbai's railway infrastructure, which is one of the most congested and overburdened in the country. With the city's population continuing to grow, the need for efficient and reliable public transportation has never been more pressing.
The Mumbai Rail Vikas Corporation has been working tirelessly to implement these projects, which are expected to have a significant impact on the city's transportation landscape. As the projects near completion, commuters can look forward to faster, more reliable, and more comfortable travel.
In conclusion, the progress of the Kalyan-Badlapur and Borivali-Virar railway projects is a welcome development for Mumbai's commuters. The completion of these projects will not only improve the city's railway infrastructure but also have a positive impact on the overall quality of life for Mumbaikars.
The significance of these projects cannot be overstated, as they will play a crucial role in shaping the future of Mumbai's transportation system. With the city's population expected to continue growing, the need for efficient and reliable public transportation will only continue to increase. The completion of these projects will be a major step forward in addressing this need and creating a better commuting experience for millions of Mumbaikars.
Frequently asked questions
What is the estimated cost of the Kalyan-Badlapur project?
The estimated cost of the Kalyan-Badlapur project is Rs 1,510 crore.
What is the expected completion date of the Borivali-Virar project?
The Borivali-Virar project is targeted for completion by 2029.