Bombay HC Approves Tata Power's 220 KV Transmission Line Upgrade
Tata Power to upgrade 75-year-old transmission line, no mangrove cutting allowed

The Bombay High Court has given the green light to Tata Power Company Ltd to upgrade its 75-year-old Kalwa-Kalyan transmission line from 110 KV to 220 KV. The upgrade aims to meet the increasing electricity demand in Greater Mumbai and Thane districts.
The court's decision comes with the condition that no mangrove trees will be cut during the project. The proposed project involves replacing 87 existing transmission towers with multi-circuit 220 KV towers.
Tata Power had assured the court that the replacement towers would be erected within the areas already occupied by the existing towers, and no mangrove trees would be cut. The company has obtained the necessary statutory approvals, including forest clearances and approval from the Maharashtra Electricity Regulatory Commission.
The project, estimated to cost Rs 488 crore, involves diversion of 4.5773 hectares of forest land. However, no mangrove trees are proposed to be felled in the 0.727-hectare Mumbai Mangrove Conservation Unit.
The company has paid Rs 2.04 crore to the Forest Department towards net present value and compensatory afforestation. Additionally, Tata Power has paid Rs 82.70 lakh towards compensatory afforestation over 9.20 hectares of degraded forest land in Murbad taluka of Thane district.
Under the approved scheme, 10,221 saplings will be planted. The court has imposed continuing monitoring requirements on Tata Power, directing the company to file detailed status and audit reports on plantation, maintenance, protection, and afforestation twice a year for the next 10 years.
The reports, supported by affidavits of the company's managing director and the Principal Chief Conservator of Forest, must be filed by January 12 and July 12 every year. Failure to file the reports or applications will be treated as contempt.
The upgrade of the transmission line is expected to improve the electricity supply in the region, meeting the increasing demand from residents and businesses. The project's completion is likely to have a positive impact on the local economy and residents' quality of life.
In conclusion, the Bombay High Court's decision to allow Tata Power to upgrade its transmission line while ensuring no mangrove trees are cut is a significant step towards meeting the increasing electricity demand in the region while protecting the environment.
Frequently asked questions
What is the purpose of the transmission line upgrade?
The upgrade aims to meet the increasing electricity demand in Greater Mumbai and Thane districts.
Will mangrove trees be cut during the project?
No, the court has ensured that no mangrove trees will be cut during the project.