Western Railway Rebuilds Bandra-Khar Flyover in 45 Days
Western Railway to rebuild Bandra-Khar flyover in 45 days. Sixth rail line project to benefit.

Western Railway is planning to rebuild the Bandra-Khar Road rail flyover in just 45 days, a significant reduction from the earlier proposed 90-day shutdown. This reconstruction is crucial for completing the Mumbai Central-Borivali sixth railway line, a key capacity expansion project under the Mumbai Urban Transport Project (MUTP).
The existing flyover carries Harbour Line trains and currently blocks the alignment required for the sixth railway line. Once rebuilt, the new structure will create the space needed to lay the additional track, allowing better segregation of suburban and long-distance train operations.
Railway officials are preparing to use precast construction technology and advanced engineering methods to complete demolition, rebuilding, and commissioning within a single mega block, subject to final approvals. The revised strategy aims to reduce inconvenience to passengers by significantly shortening the shutdown period.
The sixth line project, being implemented by Western Railway in association with Mumbai Railway Vikas Corporation (MRVC) under MUTP Phase-II, covers a 30.04-km stretch between Mumbai Central and Borivali. While the section from Khar Road to Borivali has already been commissioned, work on the remaining Mumbai Central-Khar Road stretch remains challenging due to the dense urban landscape, utility shifting, and station modifications.
According to Western Railway, most land acquisition for the project has been completed, with only a small portion of government land at Lower Parel awaiting final statutory clearances. All five Engineering Sanction Proposals have been approved, utility shifting has begun, four of the five planned electrical buildings have been completed, and signalling, telecommunication, and overhead equipment works are progressing.
The remaining work includes construction of 15 bridges, nearly 13.3 km of earthwork, new island platforms, foot over bridges, service buildings, track linking, and electrical works. The Bandra-Khar flyover reconstruction is considered one of the most complex engineering tasks in the entire project.
Western Railway also has to relocate project-affected persons in Bandra East, build new Platforms 7 and 8 at Bandra, modify existing station infrastructure, and shift several railway buildings and utilities at Mahim, Lower Parel, and Mumbai Central.
The reconstruction is expected to impact Harbour Line commuters. During the 45-day mega block, Harbour Line services between Bandra and Goregaon are likely to remain suspended or curtailed, with many trains expected to terminate at Bandra. Western Railway is preparing a detailed traffic management plan to minimize the impact on commuters.
The completion of the sixth railway line project will significantly improve the capacity and efficiency of Mumbai's suburban rail network, benefiting millions of commuters. The project is a crucial part of the Mumbai Urban Transport Project, aimed at enhancing the city's transportation infrastructure.
In conclusion, the rebuilding of the Bandra-Khar flyover in 45 days is a significant milestone in the sixth railway line project. The project's completion will have a major impact on Mumbai's transportation infrastructure, improving the lives of millions of commuters who rely on the suburban rail network every day.
Frequently asked questions
What is the purpose of rebuilding the Bandra-Khar flyover?
The rebuilding of the Bandra-Khar flyover is crucial for completing the Mumbai Central-Borivali sixth railway line, a key capacity expansion project under the Mumbai Urban Transport Project (MUTP).
How will the reconstruction impact Harbour Line commuters?
During the 45-day mega block, Harbour Line services between Bandra and Goregaon are likely to remain suspended or curtailed, with many trains expected to terminate at Bandra.