Friday, 28 August 2026 MUMBAI EDITION LIVE

CERC Framework Aids Malwa-Nimar Green Projects

New CERC framework helps renewable energy projects in Madhya Pradesh. Developers can retain grid connectivity by paying compensation.

Mumbai Alert · City Desk
Mumbai Alert · City Desk
City Desk · Mumbai Alert News · Fri, 28 August 2026 at 04:36 am
CERC Framework Aids Malwa-Nimar Green Projects

The Central Electricity Regulatory Commission (CERC) has introduced a new framework that allows eligible renewable energy projects to retain grid connectivity by paying prescribed compensation. This move is expected to benefit developers in Madhya Pradesh, particularly in the Malwa-Nimar region, where several solar and wind projects are being developed.

The framework provides relief to projects that have been delayed in achieving key milestones such as land acquisition, financial closure, and Commercial Operation Date (COD). Instead of immediate cancellation of transmission connectivity, eligible developers can seek additional time by paying compensation, provided they demonstrate tangible progress.

The Malwa-Nimar region, which includes districts such as Agar-Malwa, Shajapur, Neemuch, Mandsaur, Dhar, Khargone, Barwani, Khandwa, and Ujjain, is witnessing rapid development of solar and wind projects. For developers, grid connectivity is a critical asset, and losing an approved connection due to delays can affect project viability.

Under the CERC framework, delays in land acquisition and financial closure will attract compensation of Rs 1,000 per MW per day, while delays in achieving COD will attract Rs 3,000 per MW per day. The relief comes with conditions, and developers seeking extensions must demonstrate actual project progress.

For land and financial-closure extensions, documents covering at least 20% of the required land must be submitted. For COD extensions, land documents covering 50% to 75% of the required land, depending on the project category, are required.

The framework could be particularly useful for projects in Malwa-Nimar, where developers face challenges involving land acquisition, environmental and forest clearances, equipment and module supply, financial closure, and transmission infrastructure readiness. The region is also witnessing significant expansion of its power evacuation network, with new 220 kV and 400 kV transmission infrastructure being developed to evacuate electricity from upcoming solar and wind projects.

The CERC mechanism could ensure that projects which have made substantial progress but face genuine delays do not lose their grid access. The framework also seeks to protect valuable transmission resources, as grid connectivity, General Network Access (GNA), Inter-State Transmission System (ISTS) capacity, and evacuation infrastructure are limited resources.

Extensions have therefore been linked to demonstrable progress, preventing projects with little prospect of completion from indefinitely blocking transmission capacity. For Madhya Pradesh, particularly Malwa-Nimar, the provision could help integrate the region’s growing renewable capacity into the national grid while giving genuine projects additional time to overcome execution hurdles.

However, the relief is not unlimited, and projects failing to meet prescribed milestones even after the extension may face cancellation of grid connectivity and forfeiture of associated benefits.

The new framework is expected to provide a lifeline to renewable energy projects in Malwa-Nimar, enabling them to overcome delays and connect to the grid. This, in turn, could help increase the region’s contribution to the national renewable energy targets and promote sustainable development.

In conclusion, the CERC framework is a significant development for the renewable energy sector in Madhya Pradesh, particularly in the Malwa-Nimar region. It provides a much-needed relief to developers facing delays and challenges, while also ensuring that valuable transmission resources are protected. As the region continues to grow its renewable energy capacity, the framework is expected to play a crucial role in integrating these projects into the national grid.

Frequently asked questions

What is the CERC framework for renewable energy projects?

The CERC framework allows eligible renewable energy projects to retain grid connectivity by paying prescribed compensation.

Which region is expected to benefit from the CERC framework?

The Malwa-Nimar region in Madhya Pradesh is expected to benefit from the CERC framework.

cercrenewable energymalwa-nimarmadhya pradesh
X Facebook Telegram
Read the original report ↗

More in News

all

Raksha Bandhan 2026: 75+ Wishes and Quotes

Celebrate sibling bond with heartfelt messages. Raksha Bandhan on Aug 28.

By Mumbai Alert · City Desk · 49 min ago

all

MP High Court Upholds Shift of Rakhi Shops

Madhya Pradesh High Court supports Mhow Cantonment Board's decision, citing traffic concerns. Rakhi shopkeepers challenged the move. Court dismisses appeal.

By Mumbai Alert · City Desk · 2 hr ago

all

India Reaches 300 GW Non-Fossil Capacity Milestone

India's non-fossil fuel capacity crosses 300 GW, exceeding 54% of total capacity.

By Mumbai Alert · City Desk · 3 hr ago

all

ChatGPT Ads Launch in India with 50 Brands

ChatGPT ads start in India, 50 brands join, self-serve manager available

By Mumbai Alert · City Desk · 3 hr ago